首页 诗词 字典 板报 句子 名言 友答 励志 学校 网站地图
当前位置: 首页 > 财会考试 > ACCA/CAT > 历年真题 >

ACCA2012年6月份考试真题及答案解析(P3)(4)

2013-04-25 
读书人网精心为大家整理了ACCA2012年6月份考试真题及答案解析(P3),希望对大家的考试能带来帮助!

 7 [P.T.O.3 Introduction

  The country of Mahem is in a long and deep economic recession with unemployment at its highest since the country

  became an independent nation. In an attempt to stimulate the economy the government has launched a Private/Public

  investment policy where the government invests in capital projects with the aim of stimulating the involvement of

  private sector firms. The building of a new community centre in the industrial city of Tillo is an example of such an

  initiative. Community centres are central to the culture of Mahem. They are designed as places where people can

  meet socially, local organisations can hold conferences and meetings and farmers can sell their produce to the local

  community. The centres are seen as contributing to a vibrant community life. The community centre in Tillo is in a

  sprawling old building rented (at $12,000 per month) from a local landowner. The current community centre is also

  relatively energy inefficient.

  In 2010 a business case was put forward to build a new centre on local authority owned land on the outskirts of Tillo.

  The costs and benefits of the business case are shown in Figure 1. As required by the Private/Public investment policy

  the project showed payback during year four of the investment.

  


  Construction of the centre 2010–2011

  In October 2010 the centre was commissioned with a planned delivery date of June 2011 at a cost of $600,000 (as

  per Figure 1). Building the centre went relatively smoothly. Progress was monitored and issues resolved in monthly

  meetings between the company constructing the centre and representatives of the local authority. These meetings

  focused on the building of the centre, monitoring progress and resolving issues. Most of these issues were relatively

  minor because requirements were well specified in standard architectural drawings originally agreed between the

  project sponsor and the company constructing the centre. Unfortunately, the original project sponsor (an employee of

  the local authority) who had been heavily involved in the initial design, suffered ill health and died in April 2011. The

  new project sponsor (again an employee of the local authority) was less enthusiastic about the project and began to

  raise a number of objections. Her first concern was that the construction company had used sub-contracted labour

  and had sourced less than 80% of timber used in the building from sustainable resources. She pointed out the

  contractual terms of supply for the Private/Public policy investment initiatives mandated that sub-contracting was not

  allowed without the local authority’s permission and that at least 80% of the timber used must come from sustainable

  forests. The company said that this had not been brought to their attention at the start of the project. However, they

  would try to comply with these requirements for the rest of the contract. The new sponsor also refused to sign off

  acceptance of the centre because of the poor quality of the internal paintwork. The construction company explained

  that this was the intended finish quality of the centre and had been agreed with the previous sponsor. They produced

  a letter to verify this. However, the letter was not counter-signed by the sponsor and so its validity was questioned. In

  the end, the construction company agreed to improve the internal painting at their own cost. The new sponsor felt

  that she had delivered ‘value for money’ by challenging the construction company. Despite this problem with the

  internal painting, the centre was finished in May 2011 at a cost of $600,000. The centre also included disability

  access built at the initiative of the construction company. It had found it difficult to find local authority staff willing

  and able to discuss disability access and so it was therefore left alone to interpret relevant legal requirements.

  Fortunately, their interpretation was correct and the new centre was deemed, by an independent assessor, to meet

  accessibility requirements.

  8Unfortunately, the new centre was not as successful as had been predicted, with income in the first year well below

  expectations. The project sponsor began to be increasingly critical of the builders of the centre and questioned the

  whole value of the project. She was openly sceptical of the project to her fellow local authority employees. She

  suggested that the project to build a cost-effective centre had failed and called for an inquiry into the performance of

  the project manager of the construction company who was responsible for building the centre. ‘We need him to explain

  to us why the centre is not delivering the benefits we expected’, she explained.

  Required:

  (a) The local authority has commissioned the independent Project Audit Agency (PAA) to look into how the project

  had been commissioned and managed. The PAA believes that a formal ‘terms of reference’ or ‘project initiation

  document’ would have resolved or clarified some of the problems and issues encountered in the project. It also

  feels that there are important lessons to be learnt by both the local authority and the construction company.

  Analyse how a formal ‘terms of reference’ (project initiation document) would have helped address problems

  encountered in the project to construct the community centre and lead to improved project management in

  future projects. (13 marks)

  (b) The PAA also believes that the four sets of benefits identified in the original business case (rental savings, energy

  savings, increased income and better staff morale) should have been justified more explicitly.

  Draft an analysis for the PAA that formally categorises and critically evaluates each of the four sets of

  proposed benefits defined in the original business case. (12 marks)

  (25 marks)

 

热点排行